An open house public meeting will be held from 4:00-7:00pm on Monday, February 5, 2018 at Meadowlake Church (6501 Gilead Road) in Huntersville regarding the interchange improvements on I-77 at N.C. 73 (Sam Furr Road) and the proposed improvements to N.C. 73 from N.C. 16 to Northcross Drive. The public is invited to drop in anytime during the meeting to view maps of the proposed designs, ask questions, and provide comments to project team members in attendance or by March 12, 2018 via mail or email to Beverly Robinson at the address provided below. For the latest project information and mapping please visit the NCDOT public meetings website.
Beverly Robinson
NCDOT Project Management Unit
1578 Mail Service Center
Raleigh, NC 27699-1548
Phone: (919) 707-6041
Email: brobinson@ncdot.gov
Project description for the interchange improvements on i-77 at N.C. 73
The N.C. Department of Transportation proposed to reconfigure the I-77 and N.C. 73 (Sam Furr Road) interchange. The purpose of this project is to improve mobility and connectivity for local traffic accessing properties adjacent to this interchange. A secondary purpose is to reduce delay and congestion on N.C. 73 through the I-77/N.C. 73 interchange.
PROJECT DESCRIPTION FOR N.C. 73 Improvements from n.c. 16 to northcross drive
The purpose of the project is to increase the traffic capacity of N.C 73 and preserve long-term mobility of the corridor. A secondary purpose is to safely accommodate multi-modal uses of the corridor. Two alternatives are being developed:
- Alternative 1: Best Fit Widening Alone Existing N.C. 73.
- Alternative 2: Best Fit Widening Along Existing N.C 73 with Realignment.
(Note: Information above provided by NCDOT. Information was updated on January 24, 2018)